|
Completion 1: Midway Airport Redevelopment
Cost: $793 million
It was clear by the mid-1990s that the
increasingly decrepit Midway Airport in Chicago needed redevelopment.
Passenger traffic, surging in the years immediately before
the Sept. 11, 2001, terrorist attacks, had taken a toll on
the airport since it originally opened in 1926.
The redevelopment began in 1997, and the centerpiece is the
900,000-sq.-ft. terminal across Cicero Avenue from the old
one. The terminal is connected to the gates by a 270-ft.-long,
60-ft.-wide glass and steel pedestrian bridge across the street.
The project boasts other features as well. A 3,000-vehicle
parking garage - the first covered parking in Midway history
- stands just to the east of the terminal. A new multilevel
roadway system whisks incoming and outgoing airport traffic
away from local traffic.
Accommodating an Airport
A top issue was accommodating the continuing operation of
Midway, and phasing was critical.
The original terminal had 29 gates, while the new terminal
has 41. Each existing gate had to stay operational throughout
construction.
Each of the new gates was required to accommodate 737s, something
that was not the case at the old Midway.
The baggage and check-in were moved to the east side of Cicero.
Though the pedestrian bridge solved the problem of moving
passengers from terminal to gates, the hurdle of sending luggage
to the airplanes and back again was something else.
The solution was to locate a luggage room in the basement
of the terminal, where baggage can be sorted. The room is
connected to a baggage tunnel that runs beneath Cicero, allowing
luggage to be transported in motorized carts from the baggage
sorting area to the terminal side to the planes waiting on
the runway side.
Because of the tunnel, utilities could no longer be situated
in the Cicero right-of-way.
Another hurdle was the fact that most traffic into Midway
comes from the north along Cicero's western-most lanes, but
the new terminal is situation on the road's east side.
That required moving southbound traffic across the northbound
lanes. A ramp that exits southbound Cicero on the right-hand
side climbs over the northbound lanes to the terminal. The
ramp then passes the front of the terminal building, with
options to go to the upper level for departures or the lower
level for arrivals.
|
Key
Players
|
|
Owner:
|
Chicago Department of Aviation
|
|
General Contractor:
|
Clark/McHugh/Rausch Joint Venture, Chicago
|
|
Managing Architect:
|
A. Epstein and Sons International Inc., Chicago
|
|
Design Architect:
|
HNTB Architects Engineers & Planners, Alexandria,
Va.
|
|
Civil Engineer:
|
McDonough Associates Inc., Chicago
|
|
Plumbing/Fire Protection:
|
Globetrotters Engineering Co., Chicago
|
|
Mechanical/Electrical:
|
Environmental Systems Design Inc., Chicago
|
|
Central Heating and Refrigeration Plant:
|
Hill Mechanical, Chicago
|
Return
to Top of 2004 list
|